Select Page

BCC performed their work in a timely and efficient manner, while maintaining the utmost standards of both safety and quality.

Area Engineer
Waste Management
Turkey Run Landfill Cell Additions

Plant Barry

Southern Company, Plant Barry

Bucks, Alabama

Gypsum Pond Cell 1, Sediment Pond and Hwy 43 Modifications

Scope of Work: 

  • 60 acres of clearing and grubbing
  • 600,000 cubic yards of excavation
  • Installation of 1,600,000 square feet of HDPE liner
  • Constructed new crossing and turn lanes for facility on Alabama Highway 43
  • Miscellaneous storm drain and concrete work

Plant Barry Cel 100_0632